The rain hasn’t helped much the last few days, but we have done what we can. Officially reached the end of the first Trunk line, and beginning to work our way back laying the fiber drops and placing handholes.
Boring work starts tomorrow under a few driveways, and the start of Trunk B, a shorter run (about 2/3)
More discussions have been had with the community and paths agreed to expand the service area, and hard at work keeping those plans moving whilst delivering in the Phase 1 service area.
Comments